问题:a construction company was paid a total of 500000 for a construction project. the company's only costs for the project were for labor and materials. was the company's profit for the project greater than 150000?
(1) the company's total cost was three times its cost for materials
(2) the company's profit was greater than its cost for labor
answer is C